Post-contract implementation
Sprint prep
Sprint prep
- Outline: Ensure that the team is ready to start the next Sprint.
- Goal: Decide which Users Stories can be worked on.
- Duration: 15-30 minutes.
- Frequency: Before starting a new Sprint.
How-to
- Open the Project Board and Issue list
- Quickly assess current Sprint progress status
- Look for assigned tasks that have become irrelevant or outdated
- For irrelevant tasks: discard them on the next Sprint Planning
- For outdated tasks: update the necessary information before the next Sprint Planning
- Agree on a rough estimate of what should be achievable on the next Sprint
Note: mind the potential amount of work that will carry over before commiting to new tasks.
- Make sure all User Stories to be started have all the necessary details, including design decisions.
- Assess availability for all necessary team members (all necessary skills)